Prepared forBCS Services
ProjectAstraZeneca Mississauga Interlock
ProposalTS-2026-1017-BCS
Scope for pricing5115 Creekbank Road, Mississauga, Ontario
Drawing: Landscape Plan PC-11, Rev 02
Landscape Plan PC-11 for the AstraZeneca Mississauga interlock area

Prepared for BCS Services by Taishan Construction

AstraZeneca Mississauga Interlock

Supply and installation of 1,050 sq. ft. of Teco Block Industria interlock —
releveled, properly based, and sealed.

5115 Creekbank Road, Mississauga, OntarioOctober 17, 2026

Interlock installation proposal

Project details and confirmed pricing.

Issued to BCS Services for review. Quantities and pricing are confirmed for the interlock installation scope per Landscape Plan PC-11.

BCS Services logo
BCS SERVICESConcrete · Masonry · Excavation
Proposal statusScope and Pricing Issued
Prepared forBCS Services
Prepared byTaishan Construction
Site address5115 Creekbank Road, Mississauga, ON
Drawing referenceLandscape Plan PC-11, Rev 02
Interlock area±1,050 sq. ft.
PaverTeco Block Industria 100 mm
ScheduledOctober 22–24, 2026
Last checkedChecking secure access…
Proposal IDTS-2026-1017-BCS
Pricing$27,793.50
VersionV1 — Scope and Pricing

Drawings and site reference

Landscape Plan PC-11

Teco Block Industria paver pattern, colour mix, and installation details for the interlock area at 5115 Creekbank Road.

Project approach

How Taishan Construction delivers this scope.

A disciplined sequence from releveling to final sealing, completed within a confirmed three-day window.

01

Installed to drawing

Pavers installed to the pattern and colour mix shown on Landscape Plan PC-11, with layout control lines and verified finished elevations.

02

Releveled and properly based

The existing base is releveled to proper grade, with any underlayment material necessary and a sand setting bed on filter fabric.

03

Sealed and finished

Polymeric joining sand is swept into all joints and the completed surface receives its final sealing for a clean, durable finish.

04

Scheduled and communicated

A confirmed three-day installation window — October 22 to 24, 2026 — with one organized team from delivery to final cleanup.

Scope of work

Scope breakdown

Scope sections covering material supply through final sealing for the AstraZeneca Mississauga interlock installation, per Landscape Plan PC-11. Scheduled for October 22–24, 2026.

Mobilization, material deliveries, equipment mobilization, staging, protection of adjacent surfaces, housekeeping and demobilization are included within the installation pricing and are not charged separately.

  • Mobilization of labour, tools, and equipment
  • Delivery of releveling and compaction equipment
  • Coordination of all paver and base material deliveries
  • Establishment of material staging areas
  • Protection of adjacent surfaces, walls, and finished areas
  • Daily site housekeeping throughout installation
  • Removal of equipment and unused materials upon completion
  • Final demobilization

Investment summary

Investment summary.

All quantities are preliminary and subject to field verification, approved material selections, site access, and confirmation by BCS Services.

Material supply — approx. 1,050 sq. ft.$14,143.50$13.47 / sq. ft. · Teco Block Industria 100 mm
Labour & installation — approx. 1,050 sq. ft.$13,650.00$13.00 / sq. ft. · releveling, underlayment, final sealing
Total$27,793.50CAD · interlock installation
Mobilization & Site Preparation — IncludedInterlock Material Supply — approx. 1,050 sq. ft. — $14,143.50Installation, Releveling & Final Sealing — approx. 1,050 sq. ft. — $13,650.00

Installation schedule

A confirmed three-day schedule.

October 22–24, 2026, under normal site, weather, and material-delivery conditions.

THU22

Mobilization, Releveling & Base Preparation

Site setup, material staging, releveling of the existing base to proper grade, and underlayment preparation.

FRI23

Interlock Installation

Pavers installed to the pattern and colour mix per Landscape Plan PC-11, with cutting, fitting, and joint sand.

SAT24

Final Sealing, Cleanup & Turnover

Final sealing of the completed surface, cleanup, inspection, and handover of the finished interlock area.

Review and confirmation

Scope review
with BCS Services

Please review the scope above and confirm quantities, material selections, and site conditions.

Note: All quantities are preliminary and subject to field verification, approved material selections, site access, and confirmation by BCS Services.

Questions? Contact Jeff directly.
Interlock areaApprox. 1,050 sq. ft. (field verification required)
PaverTeco Block Industria Smooth 100 mm
Material supply$13.47 / sq. ft. = $14,143.50
Labour & installation$13.00 / sq. ft. = $13,650.00
Included in labourReleveling, underlayment, final sealing
ScheduledOctober 22–24, 2026
Drawing referenceLandscape Plan PC-11, Rev 02
Total — interlock installation$27,793.50
Scheduled startOctober 22, 2026
Request a Revision — Text 647-857-2828